Getting climate, energy & environment news right.

Dominion ordered to directly assign some transmission costs to data centers

Dominion Energy will need to change its transmission cost allocation policy to directly assign the cost of certain transmission infrastructure to the new large-load facilities — such as data centers — which made that infrastructure necessary, the Virginia State Corporation Commission said in an order filed July 31.

The mandatory contribution in aid of construction, or CIAC, will apply to “direct connect” facilities, and apply to the cost of the substations and the transmission lines which connect those facilities to the grid.

Read more in Utility Dive here.

The views and opinions expressed are those of the author’s and do not necessarily reflect the official policy or position of C3.

Thank you for signing up

Help us promote sensible solutions for both planet and prosperity.

Subscribe to our exclusive email designed for conservatives who care about climate.

Help us promote free market solutions for climate change.

5 Incredible Ways Economic Freedom Helps the Planet.

Sign up for our newsletter now to get the full list right in your inbox.

Download Now